Marshall Park Playground Construction 2014-2015


PLEASE NOTE - the playground is still under construction. It is NOT ready for use.


PLAYGROUND UPDATE from Lisa Tyler, Portland Parks 7-Jan-2015 Construction is still underway. Most of the construction should be complete by the end of January. · Play equipment and wood safety surfacing have been installed. · Benches and picnic table frames and concrete pads have been installed. · Most of the large rocks have been placed. · Large tree trucks have been place at the lower environmental education area. Next Steps · Contractor will be grading and adding rock to the main path. · The asphalt on the turnaround at the end of SW 12th drive will be repaired. NOTE: Expect the turnaround to be blocked off with no access for a few days. · Complete handrails on the wooded stairs. · Complete spreading soil and landscaping. · Complete the environmental education area. Please be cautious when walking near the construction areas.


PLAYGROUND PHOTOS 1-Jan-2015



PLAYGROUND PHOTOS 16-Nov-2014